Avoiding Disputes: Records and Sign-off

Most flooring problems can be avoided with good planning and proper testing. When questions do come up, the projects that resolve them quickly are usually the ones with clear records. This article from the Screed Scientist looks at what to record and how a simple sign-off process helps everyone on site.

It’s practical guidance, not legal advice. Contract terms and responsibilities vary between projects, so always check your own contract documents.

Why records matter

A floor passes through several hands: the screed contractor, the main contractor or site manager, sometimes a heating installer, and the flooring contractor. Each one relies on information from the others. Without written records, it’s hard for anyone to know what the conditions were, what was tested, when, and what the results showed.

Good records help to:

  • give the flooring contractor the information they need to plan their work
  • show the conditions the screed was laid and dried in
  • make it easy to answer questions later, without relying on memory
  • keep the programme moving with fewer surprises

What to record at installation

  • Date and areas laid, ideally marked on a drawing.
  • Screed type and product, including the manufacturer and any additives.
  • Specified and actual thickness in different areas.
  • Base and build-up details, such as membranes, insulation and underfloor heating.
  • Site conditions at the time: weathertight or not, temperature and general conditions.
  • Photographs of the work in progress and when finished.

What to record during drying

  • Building conditions: temperature and humidity readings, and whether doors and windows were open or closed.
  • Drying aids used: dehumidifiers, ventilation and heating, with dates.
  • Underfloor heating commissioning, if applicable, following the heating and screed manufacturers’ procedures.
  • Other trades working in the area, especially wet trades.

What to record when testing

Moisture testing is the key record before any floor finish goes down. For each test, note:

  • Test method: hygrometer (RH) test or calcium carbide (CM) test.
  • Test locations, marked on a plan.
  • Dates and times, including settling time for hygrometer tests. Settling time is normally 72 hours, but check the manufacturer’s guidelines.
  • Readings and the instrument used.
  • Conditions in the room at the time.
  • Who carried out the test.
  • The acceptable readings set by the screed, floor covering and adhesive manufacturers.

Photographs of the instrument showing each reading are simple to take and very useful.

A clear sign-off process

A sign-off doesn’t need to be complicated. It’s simply a shared point where the people involved confirm what has been done and what the next trade needs to know. A good sign-off usually covers:

  • the areas being handed over
  • the test results and methods used
  • any notes about the surface, such as areas needing preparation
  • any agreed next steps, such as further testing or a surface DPM
  • names and dates of those involved

Each party signs off for their own part of the work. If something isn’t ready, the record should say so clearly, so everyone can plan around it.

Talk early

Many issues come from assumptions: that the screed will be ready on a given date, that someone else has tested it, or that the finish can tolerate higher readings than it can. Talking early about drying times, testing and acceptable readings helps avoid that. The relevant guidance in BS 8204 and BS 8203, along with manufacturers’ data, is a useful common reference.

Keep it together

Store all of this in one place, such as a handover file or shared folder, so it’s easy to find. Our Screed Handover Checklist gives a simple list to work through.

CSC Screeding, Established in 1987, encourages clear records on every project because they make life easier for everyone involved.

Next in the series: Screed Handover Checklist