“How long until we can lay the floor?” It’s one of the most common questions on any site. The honest answer is that it depends on the screed type, its thickness and the conditions in the building. There is a standard guide, though, and understanding it helps everyone plan a realistic programme.
The standard drying guide
The figure everyone quotes is this:
- 1mm per day for the first 40mm of screed thickness, then
- 0.5mm per day beyond 40mm.
The important part is often left off: that guide is based on laboratory conditions. In a lab, temperature, humidity and airflow are controlled and steady. On a real site, conditions are rarely like that, so drying is usually slower.
The guide also shows why thickness matters so much. Because the rate halves after the first 40mm, every extra millimetre of a thicker screed adds more time than the millimetres before it.
What slows drying on site
Common reasons a screed dries more slowly than the guide suggests include:
- Cold weather. Cold air holds less moisture than warm air, so evaporation slows down.
- High humidity. If the air in the room is already damp, it can’t take much more moisture from the screed.
- Poor ventilation. Moisture leaving the screed needs somewhere to go. In a closed, still room the air quickly becomes saturated.
- A building that isn’t weathertight. Rain getting in, or wet trades working nearby, adds moisture back into the space.
- Extra thickness. Areas laid thicker than planned, for example to make up levels, take longer.
- Other wet work. Plastering and other wet trades in the same area raise the humidity.
Sand and cement screed
Traditional sand and cement screed is mixed with water, laid and compacted. It dries by losing water through its surface. Thickness and site conditions have a big effect on how long that takes, and the standard guide above is a useful starting point for planning, as long as everyone remembers it describes lab conditions.
Flowing screed
Flowing screed is pumped in and self-levels, which makes it quick to install. CSC Screeding can lay up to 1,000m² a day of flowing screed on suitable projects.
Calcium sulphate flowing screed behaves differently from sand and cement as it dries. One practical advantage is that flowing screed can be force dried after 7 days, for example with dehumidifiers or by bringing underfloor heating up gradually, in line with the manufacturer’s guidance. Our article How to Speed Up Drying Safely explains how to do this properly. Force drying is not suitable for traditional sand and cement screed, which must be left to dry naturally.
Calcium sulphate screeds can also be sensitive to some finishes and adhesives while they still hold moisture, so the manufacturer’s guidance on acceptable moisture readings and surface preparation should always be followed.
Proprietary and fast-drying screeds
Many manufacturers produce proprietary screeds and additives designed to dry or be ready for floor finishes sooner. Their drying claims apply when their own instructions are followed, so always use the manufacturer’s data sheet for those products rather than the general guide.
Drying time is a guide, not a test
No calendar can tell you that a screed is ready. The drying guide is for planning. The decision to lay a floor finish should be based on proper moisture testing, using the hygrometer test or the calcium carbide (CM) test, and checked against the readings the screed, floor covering and adhesive manufacturers accept. See How to Test Screed Moisture Properly.
BS 8204 gives guidance on screeds and BS 8203 covers installing resilient floor coverings. Both are worth referring to alongside the manufacturers’ data.
Planning tips
- Agree screed thickness early and keep it consistent where possible.
- Build realistic drying time into the programme, allowing for site conditions.
- Get the building weathertight and keep conditions steady.
- Plan when testing will happen, and who will do it.
- Keep a record of conditions and readings.
Next in the series: How to Speed Up Drying Safely